Vale House, Tunbridge Wells, TN1
Office to residential conversion
£6.2m
24 months
Role: Project Management
Notes: Prior Approval for the change of use from Office (B1) use to Residential (C3), forming 60 no. units, required that project is to be completed within 3 years of planning approval. When works on site commenced, Client had only 18 months left to comply with this condition. The critical path items have been moved forward in the plan to allow for any unforeseen delays. Completion was achieved two months before the deadline.